Project Name
Projects
Previous Next

June, 2011

Client
Water Undertaker

Gloucestershire


Share
/ Linkedin /

Strategic Water Main

Brief

  • 17km strategic water main
  • Referencing 2 different route corridors
  • Highlighting all risks & constraints associated with each route
  • Pre-scheme consultations with all grantors and negotiating route
  • Arranging access for environmental and engineering surveys
  • Negotiating compensation claims following surveys
  • Checking notice plans and legal titles in preparation for serving s.159 notices

Risks & Constraints

  • Impact on mines and minerals
  • Weather and ground conditions
  • Archaeology
  • River, motorway and rail crossings
  • Land drainage

Solutions

  • Detailed pre scheme consultation
  • Detailed route feasibility study exploring all options
  • Detailed drainage design
  • Detailed working method statement agreed
  • Close relationship with landowners, occupiers and agents
  • Proactive stance during construction – identifying concerns early
  • Regular presence on site


Contact: Andrew Barker

D: 01270 446412

E: Andrew.Barker@dalcourmaclaren.com